Rolling EoI for Empanelment of Arbitrators

MENU

Shifting and modification work of 4th major EHT line of POWER GRID

NCRTC has completed shifting and modification work of 4th major and important EHT line of POWER GRID i.e. 400KV, Single

NCRTC has completed shifting and modification work of 4th major and important EHT line of POWER GRID i.e. 400KV, Single Circuit (Dadri – Panipat II), near S.R.M. University Muradnagar (Ghaziabad). With this, a total of 23 EHT lines infringing Delhi-Ghaziabad-Meerut RRTS Corridor have been shifted. The shifting and modification work was carried out by following Standard Operating Procedure (SOP) in view of the COVID-19 outbreak which includes the thermal screening of officials and labourers, the use of sanitizers and maintaining social distance.

Recent Posts